Batteries for UK’s Capacity Market stay short duration, despite lower de-rating factors

LinkedIn
Twitter
Reddit
Facebook
Email
Vattenfall’s Parc y Cymoedd site in Wales, UK. Image: Vattenfall.

The vast majority of battery projects set to compete in Britain's upcoming Capacity Market (CM) auctions will face significantly decreased de-rating factors after it emerged that most projects are still set to use either 30 minute or one hour duration batteries.

The latest update from transmission system operator National Grid’s Electricity Market Reform (EMR) delivery body, which facilitates the CM, has shown the majority (~62%) of batteries proposed for the T-1 (projecs with capacity to be delivered during 2018-2019) offer an hour’s duration, with 36% being 30 minute batteries. Similarly, the T-4 update (for projects to be developed and delivered by 2021-2022), shows a fairly even split across the two most popular duration periods, with ~44% offering 30 minute discharge and 42% an hour.

This article requires Premium SubscriptionBasic (FREE) Subscription

Enjoy 12 months of exclusive analysis

  • Regular insight and analysis of the industry’s biggest developments
  • In-depth interviews with the industry’s leading figures
  • Annual digital subscription to the PV Tech Power journal
  • Discounts on Solar Media’s portfolio of events, in-person and virtual

Or continue reading this article for free

The longest duration battery in the T-1 offers two hours alongside two 90 minute projects, while the T-4 offers a number of two and four hour duration batteries in addition to a small proportion of six hour pumped hydro projects.

However, with a combined battery storage capacity of 4.5GW across the two schemes, new de-rating factors recently implemented by the Department of Business, Energy and Industrial Strategy (BEIS) mean that developers will only have access to revenues from less than 1.3GW.

The update from the EMR body, published late on Friday (12 January) afternoon, shows the projects left to compete following changes to prequalification decisions, credit cover requirements and outstanding prequalification reasons.

Planning consent status was also included, with the deadline for this extended to this month following the publication of new de-rating factors in early December.

The number of batteries set to compete in the upcoming auctions has fallen significantly since December’s initial results, with 29 prequalified projects lost from the T-1 – down to 74 – and 82 lost from T-4, which now has 145 prequalified battery projects.

This suggests a number of developers opted to cut their losses since December’s initial results and it is now unclear if or how these projects will be brought to market without a CM contract. With many offering short duration capability for frequency response, it is likely many will try to win firm frequency response (FFR) contracts in a rapidly diminishing market as National Grid prepares a new suite of service products.

However, some batteries that failed to secure initial prequalification in the CM, such as Vattenfall’s 22MW EFR battery at Parc y Cymoedd, have returned following the Tier 2 appeals process. Aggregators Kiwi Power and Limejump, which had swathes of capacity rejected in December, have also had projects conditionally approved in both auctions while the UK’s first subsidy-free solar farm Clayhill remains locked out.

These projects remain ‘conditionally prequalified’ as they have yet to post credit cover and must now do so in time to confirm entry into the auctions.

If they do not post credit cover in time, but do post it in the regulated timeline of 15 working days from status change, they will have the opportunity to decide to take an agreement at the clearing price. 

The projects will now compete at the end of the month in the T-1 auction, slated to start on 30 January, before the T-4 process will kick off on 6 February. 

In December, some commentators and industry participants in UK had expressed a belief that de-rating rules could push the sector towards longer-duration batteries, while potentially sparking a shift towards energy arbitrage as a source of revenue for shorter duration applications. Later that month, Solar Media Market Research analyst Lauren Cook blogged for Energy-Storage.News that the pre-qualification register for the Capacity Market had driven the UK's utility-scale battery storage pipeline up to almost 8GW.

11 November 2025
San Diego, USA
The 2024 Summit included innovative new features including a ‘Crash Course in Battery Asset Management’, Ask-Me-Anything formats and debate-style sessions. You can expect to meet and network with all the key industry players again in 2025 from major US asset owners, operators, RTOs and ISOs, optimizers, software and analytics providers, technical consultancies, O&M technology providers and more.

Read Next

April 17, 2025
Clean energy trade body American Clean Power Association (ACP) has released a report on energy storage market reforms for regional grid operators based on findings from the Brattle Group.
April 17, 2025
Battery storage developer and operator Spearmint Energy has secured US$250 million for two battery energy storage system (BESS) projects located in Texas, US, totalling 400MWh.
April 17, 2025
US non-lithium battery technology companies Eos Energy Enterprises and Unigrid have announced partnerships to deploy their tech abroad, striking deals in the UK and India respectively.
Premium
April 17, 2025
Owner-operator BW ESS’ 100MW/331MWh UK Bramley BESS was unique in numerous ways when it came online last year, the first outside China to use Sungrow’s AC block technology.
April 17, 2025
A proposed landowner-led 576MWh solar-plus-storage site in Tasmania has been added to Australia’s Environment Protection and Biodiversity Conservation (EPBC) Act.

Most Popular

Email Newsletter