FlexGen, SMT Energy commission 320MWh Texas BESS in just six weeks, as ERCOT grid faces record demand

LinkedIn
Twitter
Reddit
Facebook
Email

Developer SMT Energy and Software-focused energy storage system integrator FlexGen have announced the start of operations of a 160MW/320MWh energy storage facility in Houston, Texas, US.

Announced 9 September, the Houston IV battery energy storage system (BESS) project joins more than 12 projects from SMT and FlexGen built to support the Electric Reliability Council of Texas (ERCOT) grid.

Engineering, procurement, and construction (EPC) services were provided by Irby Construction Company.

In February 2025 SMT secured a US$135 million funding for the Houston IV project, then in May, SMT and utility CenterPoint Energy broke ground on the project.

This article requires Premium SubscriptionBasic (FREE) Subscription

Try Premium for just $1

  • Full premium access for the first month at only $1
  • Converts to an annual rate after 30 days unless cancelled
  • Cancel anytime during the trial period

Premium Benefits

  • Expert industry analysis and interviews
  • Digital access to PV Tech Power journal
  • Exclusive event discounts

Or get the full Premium subscription right away

Or continue reading this article for free

SMT and FlexGen highlighted that Houston IV was commissioned in six weeks, “cutting the time of deployment by 3x from the original timeline.”

The BESS project comes at a meaningful time for ERCOT, setting a new hourly peak load record on 22 July of 91.1GW, according to the US Energy Information Administration (EIA).

Occurring during a heat wave, the 22 July peak was 6% greater than the previous peak load record of 85.5GW on 10 August 2023. EIA said it was met with 48% of generation from natural gas and 32% from solar.

In May, ERCOT initiated a programme to encourage BESS and other inverter-based resources to adopt grid-forming technology.

The Nodal Protocol Revision Request (NPRR) “establishes a one-time advanced grid support incentive programme to encourage inverter-based resources (IBRs) that would not otherwise be required to provide advanced grid support to implement advanced grid support within 18 months of receiving the award notification.”

According to ERCOT documents detailing the programme, ERCOT staff reviewed NPRR, which was introduced with the intention of making the market an “industry leader for grid reliability and resilience”, and said it would have a positive market impact.

In April 2025, Trina Storage partnered with FlexGen on a 371MWh BESS for SMT, also in Houston. That project uses Trina Storage’s Elementa 2 BESS solution.

Earlier this year, FlexGen acquired Clean Energy Services, a US-based services company that has commissioned over 15GWh of BESS projects. The financial terms of that deal were not disclosed.

In June, FlexGen announced it would be entering the European market via projects in the Nordics, UK, Portugal, and Ukraine.

Battery Asset Management Summit USA 2026 will be held 15-16 September in Garden Grove, California, hosted by Energy-Storage.news publisher Solar Media (part of the Informa Group). The agenda emphasises addressing the roles of AI, cybersecurity, and second-life applications, broken down into two tracks: Technical Asset Management and Commercial Asset Management. This year, the conference is also co-located with Solar & Storage Finance Summit USA. Visit the official site for more details.

26 November 2026
9am GMT / 1pm GST
In this webinar, Florian Didier and Salomé Perperot from Clean Horizon share the approach they use when supporting IPPs through optimiser selection and contract negotiation across Europe. The presentation will be followed by a live Q&A session in which attendees can put their own questions to the speakers. Who should attend: IPPs and developers, asset owners and investors, lenders and financial advisors, and anyone involved in the commercial structuring of battery storage projects.
22 February 2027
InterContinental London - The O2, London, UK
The Future of Energy Storage Starts Here Three days in London where developers, IPPs, investors, utilities and the manufacturers building the technology come to close deals, not swap business cards. If you need to be in the room with the people deploying capital into European storage, this is that room.
20 April 2027
Renaissance Dallas at Plano Legacy West Hotel, Dallas, Texas, Dallas
Policy, Procurement and Power Demand: Defining the Next Chapter for Energy Storage. Two days in Dallas where developers, IPPs, investors, utilities and the manufacturers building the technology come to close deals, not swap business cards. If you need to be in the room with the people deploying capital into US storage, this is that room.

Read Next

November 26, 2026
NYSE-listed energy infrastructure company Energy Vault has reported its Q3 2026 financial results and the close of non-recourse project financing for its 150MW/300MWh SOSA Energy Centre in Texas, US.
November 26, 2026
The first units of a BESS have arrived at European Energy’s operational Mokoan solar PV plant in northern Victoria, Australia.
November 25, 2026
A grid-scale battery energy storage system (BESS) planned for the Yukon Territory of northern Canada has lost its contractor, Canadian battery storage engineering and construction company SunGrid.
Premium
November 25, 2026
Energy-Storage.news speaks with Trina Storage’s Mike Watson about the company’s genset-BESS solution and its approach to safety.
Premium
November 25, 2026
Elias Saba of Eku Energy spoke to ESN Premium about how data centre demand for shared equipment is affecting BESS development.