FlexGen, SMT Energy commission 320MWh Texas BESS in just six weeks, as ERCOT grid faces record demand

LinkedIn
Twitter
Reddit
Facebook
Email

Developer SMT Energy and Software-focused energy storage system integrator FlexGen have announced the start of operations of a 160MW/320MWh energy storage facility in Houston, Texas, US.

Announced 9 September, the Houston IV battery energy storage system (BESS) project joins more than 12 projects from SMT and FlexGen built to support the Electric Reliability Council of Texas (ERCOT) grid.

Engineering, procurement, and construction (EPC) services were provided by Irby Construction Company.

In February 2025 SMT secured a US$135 million funding for the Houston IV project, then in May, SMT and utility CenterPoint Energy broke ground on the project.

This article requires Premium SubscriptionBasic (FREE) Subscription

Try Premium for just $1

  • Full premium access for the first month at only $1
  • Converts to an annual rate after 30 days unless cancelled
  • Cancel anytime during the trial period

Premium Benefits

  • Expert industry analysis and interviews
  • Digital access to PV Tech Power journal
  • Exclusive event discounts

Or get the full Premium subscription right away

Or continue reading this article for free

SMT and FlexGen highlighted that Houston IV was commissioned in six weeks, “cutting the time of deployment by 3x from the original timeline.”

The BESS project comes at a meaningful time for ERCOT, setting a new hourly peak load record on 22 July of 91.1GW, according to the US Energy Information Administration (EIA).

Occurring during a heat wave, the 22 July peak was 6% greater than the previous peak load record of 85.5GW on 10 August 2023. EIA said it was met with 48% of generation from natural gas and 32% from solar.

In May, ERCOT initiated a programme to encourage BESS and other inverter-based resources to adopt grid-forming technology.

The Nodal Protocol Revision Request (NPRR) “establishes a one-time advanced grid support incentive programme to encourage inverter-based resources (IBRs) that would not otherwise be required to provide advanced grid support to implement advanced grid support within 18 months of receiving the award notification.”

According to ERCOT documents detailing the programme, ERCOT staff reviewed NPRR, which was introduced with the intention of making the market an “industry leader for grid reliability and resilience”, and said it would have a positive market impact.

In April 2025, Trina Storage partnered with FlexGen on a 371MWh BESS for SMT, also in Houston. That project uses Trina Storage’s Elementa 2 BESS solution.

Earlier this year, FlexGen acquired Clean Energy Services, a US-based services company that has commissioned over 15GWh of BESS projects. The financial terms of that deal were not disclosed.

In June, FlexGen announced it would be entering the European market via projects in the Nordics, UK, Portugal, and Ukraine.

Battery Asset Management Summit USA 2026 will be held 15-16 September in Garden Grove, California, hosted by Energy-Storage.news publisher Solar Media (part of the Informa Group). The agenda emphasises addressing the roles of AI, cybersecurity, and second-life applications, broken down into two tracks: Technical Asset Management and Commercial Asset Management. This year, the conference is also co-located with Solar & Storage Finance Summit USA. Visit the official site for more details.

13 October 2026
London, UK
Now in its second edition, the Summit provides a dedicated platform for UK & Ireland’s BESS community to share practical insights on performance, degradation, safety, market design and optimisation strategies. As storage deployment accelerates towards 2030 targets, attendees gain the tools needed to enhance returns and operate resilient, efficient assets.
3 November 2026
Málaga, Spain
Understanding technology and supplier selection for Europe’s utility-scale PV market in 2027. PV ModuleTech Europe 2026 is a two-day conference that tackles these challenges directly, with an agenda that addresses all aspects of PV module, inverter and battery supplier selection; product availability, technology offerings, supply chain traceability, quality assurance, factory auditing, system reliability, and supplier bankability.

Read Next

September 18, 2026
In this US news roundup, Eos has received an advance on its DOE loan, FlexGen and Lighshift have partnered on 16 BESS projects, and Georgia Power has energised a 128MW BESS.
September 18, 2026
US battery energy storage system (BESS) developer-operator Jupiter Power has closed a US$1.4 billion financing, supporting 10 US BESS projects totalling 3,600MWh of capacity.
September 18, 2026
The US has pledged financial support towards an existing 400MWh battery energy storage system (BESS) portfolio in Ukraine.
September 18, 2026
All BESS and demand response projects selected under ASL’s 2023 firming tender for New South Wales, Australia, are now operational.
Premium
September 17, 2026
Energy-Storage.news Premium speaks with Randolph Mann, CEO at developer esVolta at the 2026 US Battery Asset Management Summit in Garden Grove, California.