UK BESS fund Harmony Energy Income Trust scraps dividend, considers selling portfolio

LinkedIn
Twitter
Reddit
Facebook
Email

Harmony Energy Income Trust (HEIT) has scrapped its first quarter dividend and appointed advisors JLL to sell some or all of its BESS assets, partly to demonstrate that the fund is undervalued by the markets.

Despite a 48% quarter-on-quarter increase in revenues in the three months to 30 April, the firm has now engaged JLL to “seek offers for some or all of the company’s assets, in order to maximise value and demonstrate the continuing disconnect with the share price,” it said yesterday (30 May). Its share price is down 57% compared to a year ago.

This article requires Premium SubscriptionBasic (FREE) Subscription

Enjoy 12 months of exclusive analysis

  • Regular insight and analysis of the industry’s biggest developments
  • In-depth interviews with the industry’s leading figures
  • Annual digital subscription to the PV Tech Power journal
  • Discounts on Solar Media’s portfolio of events, in-person and virtual

Or continue reading this article for free

The fund, which is managed by developer Harmony Energy and trades as HEIT, has five operational UK battery energy storage system (BESS) projects and three set to be commissioned this year, all in all totalling 395.4MW/790MWh. Those include the two joint-largest operational systems in the UK and Europe, Pillswood and Bumpers at 198MWh each.

The decision to appoint JLL comes as HEIT scrapped its first quarter dividend, which was initially set to only be postponed. It said it does not anticipate being in a position to pay a dividend for the remainder of the current financial year, which runs to 31 October.

Revenues for all BESS projects in the UK fell dramatically in 2023 as ancillary service markets saturated. Other funds, like Gore Street Capital’s, have managed to partially offset this by going into newer markets in the US and Europe.

Revenues have recovered since then, HEIT said, thanks to growing day-ahead wholesale price spreads, revenue opportunities in the Balancing Mechanism (BM) and higher prices in the ancillary service markets.

The company’s three remaining BESS projects – Rusholme, Wormald Green and Hawthorn Pit – have also had their commercial operation dates (COD) pushed back to Q3 2024, the first because of minor delays to a distribution network operator’s (DNO) connection programme, and the other two because of balance of plant (BOP) contractor delays.

Harmony Energy is engaging the contractor to expedite completion of the Wormald Green and Hawthorn Pit projects as soon as possible, while also exercising its contractual rights to claim liquidated damages to compensate for the lost revenue opportunities.

The falling revenues in the UK market has led to a swathe of investors buying up BESS developer-operators and their portfolios, a trend explored in a recent Energy-Storage.news article (Premium access).

Read Next

April 16, 2025
With over 9GWh of operational grid-scale BESS (battery energy storage system) capacity in the UK – and a strong pipeline – it’s worth identifying the regional hotspots and how the landscape may evolve in the future. 
April 11, 2025
UK regulator Ofgem has launched a cap and floor investment support scheme to unlock funding for new Long Duration Electricity Storage (LDES).
April 7, 2025
Gilkes Energy has been awarded planning consent for its Earba Pumped Storage Hydro (PSH) scheme.
April 3, 2025
Invinity Energy Systems has been given the green light to deploy a 20.7MWh vanadium redox flow battery system in the UK, the largest in the country.
Premium
April 3, 2025
The UK saw 1,590MW/3,179MWh of grid-scale BESS projects approved last month, bringing the total approved projects to around 55.4GW/117GWh.

Most Popular

Email Newsletter