Wirsol and Edify connect 60MW solar farm in Victoria, storage retrofit imminent

LinkedIn
Twitter
Reddit
Facebook
Email

Edify Energy and Wirsol Energy have connected the 60MW Gannawarra Solar Farm in northwest Victoria to the grid, with a storage retrofit expected before the summer.

The solar farm is connected on site to Powercor’s 66kV distribution line between Swan Hill and Kerang, providing access to Victoria’s power grid. The commissioning process has commenced and once in full production it will provide power to around 18,100 Victorian households. 

This article requires Premium SubscriptionBasic (FREE) Subscription

Enjoy 12 months of exclusive analysis

  • Regular insight and analysis of the industry’s biggest developments
  • In-depth interviews with the industry’s leading figures
  • Annual digital subscription to the PV Tech Power journal
  • Discounts on Solar Media’s portfolio of events, in-person and virtual

Or continue reading this article for free

The solar farm, which is spread over 132 hectares, will be integrated with the Gannawarra Energy Storage System – a 25MW / 50MWh Tesla Powerpack battery – developed by Edify Energy and owned jointly by Wirsol Energy and Edify Energy. The project will therefore demonstrate how existing PV projects can be successfully retrofitted with battery storage.

This element of the project is expected to be completed before the summer this year, at which time the Gannawarra Energy Storage System and the Gannawarra Solar Farm will be amongst the largest integrated solar and storage facilities in the world. This project also features a first-of-its-kind long-term commercial services agreement with the utility EnergyAustralia, who will operate the battery in conjunction with its offtake from the Gannawarra Solar Farm. 

Mark Hogan, managing director of Wirsol Energy, said: “The Gannawarra solar farm is in every respect a world leading project and is testament to the future role of solar in enhancing energy supply across Australia.”

Read Next

April 17, 2025
A proposed landowner-led 576MWh solar-plus-storage site in Tasmania has been added to Australia’s Environment Protection and Biodiversity Conservation (EPBC) Act.
April 17, 2025
Federation Asset Management has announced its intention to launch a new long-duration energy storage (LDES) investment platform in Australia.
April 16, 2025
Wisconsin, US utility Madison Gas and Electric (MGE) is partnering with We Energies and Wisconsin Public Service (WPS) to purchase 30MW of solar capacity and 16.5MW of battery storage from the High Noon Solar Energy Centre.
Premium
April 16, 2025
In this blog, ESN Prmeium speaks with Dr Thomas Nann, CEO and co-founder of Allegro Energy on its microemulsion flow battery.
April 16, 2025
Quinbrook has officially confirmed the expansion of the ‘Supernode’ BESS in Queensland, Australia, via a 1,010MWh offtake agreement.

Most Popular

Email Newsletter